Changeovers & lot sizing

Shorter switches between products, and run lengths that balance changeover time against inventory.

3 min gist, 9 min in full Draft, review pending

Read atChange any time

Why faster changeovers mean smaller batches, less stock and more flexibility.

A changeover is the time a line stands idle while it switches from one product to the next: cleaning tanks, swapping moulds, changing labels, running test samples. If a changeover takes 90 minutes, nobody wants to do it often, so the plant runs long batches. Long batches mean big piles of stock and a slow response when demand shifts.

That’s the classic trade-off in lot sizing: fewer, longer runs save changeover time but build inventory; shorter runs keep stock low but lose capacity to changeovers. It is the production version of EOQ, with the changeover playing the role of the ordering cost.

The way out is to make changeovers shorter. SMED (single-minute exchange of die), developed by Shigeo Shingo, works in three steps:

  1. Separate internal work, which can only be done with the line stopped, from external work, which can be done while it runs.
  2. Move as much as possible to external: pre-stage the next labels, pre-mix the next batch, pre-heat the moulds.
  3. Streamline what remains with quick-release fittings, standard settings and practised teams.

If a 90-minute changeover drops to 30, the plant can switch three times as often for the same lost time. Batches shrink, inventory falls and the line can follow demand more closely.

Many process plants also use a product wheel: a fixed, repeating sequence of products, ordered to make each changeover as easy as possible.

Words to use

SMED
Single-minute exchange of die: a method for cutting changeover time, aiming for under 10 minutes.
Internal vs external setup
Work that needs the line stopped versus work that can be done while it runs.
Product wheel
A repeating production sequence designed to keep changeovers short.

How changeover time limits the product wheel, the arithmetic of SMED, and a 90-minute changeover cut to 30.

Changeovers eat capacity

On a line making several products, time is spent either running or changing over. If running the required volumes uses a fraction ρ\rho of the line’s time, only 1−ρ1 - \rho is left for changeovers. A product wheel that runs each product once per cycle of length TT needs:

T≥∑si1−ρT \ge \frac{\sum s_i}{1 - \rho}

where sis_i are the changeover times in the cycle. Each product’s batch must cover demand for one whole cycle, so batch sizes and cycle stock grow in proportion to TT.

Worked example: three shampoos on one line

Running the three products takes 80% of the line’s time (ρ\rho = 0.8), and each changeover takes 90 minutes.

  • Shortest feasible wheel: 3×1.5/(1−0.8)=22.53 \times 1.5 / (1 - 0.8) = 22.5 hours of line time.
  • Cut each changeover to 30 minutes: 3×0.5/0.2=7.53 \times 0.5 / 0.2 = 7.5 hours.

The wheel turns three times as often, each batch is a third of the size, and cycle stock falls by about two thirds, with the same share of time lost to changeovers.

In practice, plan the wheel somewhat longer than the minimum to leave room for breakdowns and demand swings.

SMED in practice

Element of the 90-minute changeoverBeforeAfterHow
Waiting for the next labels and caps20 min0Staged at the line before the stop (now external)
Fetching tools and parts15 min0Changeover cart prepared in advance (external)
Cleaning the filler30 min20 minQuick-release parts, two people working in parallel
Adjustments and test runs25 min10 minFixed settings and go/no-go gauges replace trial and error
Total line stop90 min30 min

The order matters: first move work outside the stop (often half the gain at almost no cost), then simplify what must stay inside it.

Sequence-dependent changeovers, where changeovers really cost money, lot sizing under capacity limits, and measuring changeovers honestly.

Sequence matters

Many changeovers depend on what ran before. In shampoo or paint, light to dark colours is quick and dark to light needs a full clean; in food, allergen-free products run before those with allergens; in plastics, low-melt materials before high. Finding the best order is like the travelling salesman problem (visit every product once at the lowest total changeover). Product wheels fix a good sequence and repeat it, which also makes the plant predictable for planners and suppliers.

Where changeovers really cost money

  • At the bottleneck: a changeover hour is a lost hour of plant output, worth the bottleneck’s throughput per hour.
  • Away from the bottleneck: a changeover uses spare time and costs little beyond labour and materials. Running smaller batches there is almost free.

So SMED effort should go first to the bottleneck, and batch-size rules should differ between bottleneck and non-bottleneck resources.

Lot sizing under capacity limits

With several products sharing a line and limited capacity, choosing batch sizes becomes a scheduling problem in its own right. In the research literature it appears as the economic lot scheduling problem, often solved with a common-cycle rule (every product once per cycle) or with cycles that are multiples of a base period, so fast movers run every cycle and slow movers every second or fourth. In process industries, campaigns group several batches of similar products to reduce cleaning and validation effort.

Measuring changeovers honestly

Measure from the last good unit of the old product to the first good unit of the new product at full speed. Ramp-up time at reduced speed and the scrap during start-up are part of the changeover, and leaving them out hides much of the loss. Track the changeover time per changeover type, and investigate the long tail rather than the average.

Interview kit

Practise it out loud

Answer each question yourself before opening the model answer.

Say it in 30 seconds

Changeovers create a lot-sizing trade-off: long runs save setup time but build inventory; short runs keep inventory low but lose capacity. Rather than just optimizing batch size, I’d attack the changeover itself with SMED, moving setup work outside the stoppage and streamlining the rest. Shorter changeovers make smaller batches economical, which cuts inventory and improves responsiveness.

How does reducing changeover time reduce inventory?

Changeover time is the fixed cost that justifies big batches. When it shrinks, the economic batch size shrinks too, roughly with the square root of the setup cost. Smaller batches mean less cycle stock and quicker response to demand changes.

What is the first step in SMED?

Separate internal setup, which needs the machine stopped, from external setup, which can be done while it runs. Just moving preparation, such as fetching tools, materials and paperwork, outside the stoppage often removes a large share of the changeover time without any investment.

Connected stops

Where this idea feeds in, or gets its inputs from.

Sources and further reading

  1. Shingo, S. (1985). A Revolution in Manufacturing: The SMED System. Productivity Press.
  2. Silver, E. A., Pyke, D. F. & Thomas, D. J. (2017). Inventory and Production Management in Supply Chains (4th ed.). CRC Press.
  3. King, P. L. (2009). Lean for the Process Industries: Dealing with Complexity. Productivity Press.

Reading settings

Saved on this device. Changes apply as you choose them.

Theme
Text size
Typeface for reading
Line spacing
Line length
Start each topic at

Deeper levels stay one click away whichever you choose.

Preview

Safety stock covers the surprises while you wait for a delivery. It grows with the square root of lead time, not with lead time itself.

Lines

↑ ↓ move ↵ open Topics marked “Soon” open their line