What a supply chain is

The stages, the three flows that connect them, and the push–pull boundary that splits planning from reacting.

3 min gist, 9 min in full Draft, review pending

Read atChange any time

Stages, three flows, and the line between planning ahead and reacting to orders.

Think about a bottle of shampoo in a kirana store. Before it got there, a chemical supplier made the surfactants, a packaging supplier moulded the bottle, a factory filled and packed it, a warehouse stored it, a distributor delivered it, and the store put it on the shelf. All of those stages, plus the customer who buys it, form a supply chain.

Three things flow through it:

  • Product flows mostly downstream, from suppliers to customers, and some flows back as returns.
  • Information flows both ways: orders and sales data upstream, delivery plans and invoices downstream.
  • Money flows upstream as each stage pays the one before it.

Supply chain management is coordinating all three so the customer gets the product when and where they want it, at the lowest total cost. The total matters, because a choice that saves money in one stage, such as huge factory batches, can cost more elsewhere, in warehouse space and stale stock.

One useful idea is the push–pull boundary:

  • Push steps run ahead of demand, on forecasts: the factory makes shampoo before anyone orders it.
  • Pull steps run in response to an actual order: a custom laptop is assembled only after you click “buy”.

Where the boundary sits shapes everything: inventory is held just before it. Shampoo is pushed almost all the way to the shelf; a made-to-order sofa is pulled from much earlier.

Words to use

Push vs pull
Acting ahead of demand on forecasts, versus acting in response to actual orders.
Push–pull boundary
The point where work switches from forecast-driven to order-driven; stock sits just before it.
Make to stock vs make to order
Producing ahead of orders, versus producing only after an order arrives.

The four cycles of a supply chain, the three kinds of decision, and a shampoo traced from chemical plant to shelf in days.

Four cycles

A supply chain can be read as a series of cycles, each linking two stages and each starting with an order:

CycleBetweenTriggered by
Customer orderCustomer and retailerA customer buying or ordering
ReplenishmentRetailer and distributorThe retailer’s stock running down
ManufacturingDistributor and manufacturerReplenishment orders or a forecast
ProcurementManufacturer and suppliersThe production plan

Each cycle has its own steps (the buyer orders, the supplier fulfils and delivers, the buyer receives and pays) and its own people and systems. Problems often appear at the hand-offs between cycles.

Three kinds of decision

  • Design (years): where plants and warehouses go, what to make or buy, which modes and partners to use.
  • Planning (months to a year): how much to produce where, which markets each site serves, inventory targets, promotions.
  • Operation (days to weeks): which order ships today, from where, on which truck; which line runs which product.

Each level sets the limits for the next one down, as the planning hierarchy stop explains.

Worked example: a shampoo's 72 days

Typical times between a surfactant being made and the shampoo being sold:

StageDays
Transit, chemical supplier to plant5
Raw material stock at the plant15
Production and packing2
Finished goods at the plant10
Transit to the distribution centre3
Stock at the distribution centre20
At the distributor7
On the store shelf10
Total72

Only about 2 of those 72 days change the product; the rest is moving and waiting. Most of a supply chain’s inventory, and much of its cost, sits in that waiting, which is why end-to-end lead time is such a powerful measure.

Where the term came from, the SCOR process model, local versus global optimization, and why supply chains are really networks.

Where the idea came from

Logistics, purchasing and production were long managed as separate functions. The term “supply chain management” was popularized in the early 1980s by consultants Keith Oliver and Michael Webber, who argued that the flow from suppliers to customers should be managed as one system, with inventory and service decided across functions rather than within each.

The SCOR model

The Supply Chain Operations Reference model, maintained by ASCM, gives a standard vocabulary for supply chain processes and metrics. The classic version organized processes as Plan, Source, Make, Deliver, Return and Enable; the newer SCOR Digital Standard uses Orchestrate, Plan, Order, Source, Transform, Fulfill and Return. Companies use it to map their processes, compare performance on common metrics and find gaps.

Local versus global

Decisions that look good for one stage often hurt the whole:

  • Purchasing buys a year’s supply to get a discount; the warehouse fills up and part of it becomes obsolete.
  • The plant runs long batches to cut changeover costs; distribution centres hold months of stock.
  • Sales books a big end-of-quarter order with a special discount; production pays overtime and next quarter’s orders fall.

Managing the supply chain means making these trade-offs visible and judging them on total cost and service, which usually requires shared measures and incentives across functions.

Chains are really networks

Real supply chains are networks: many suppliers at each tier, several plants, many channels and customers, with service providers (logistics companies, banks, IT providers) supporting the flows. Decisions at one point ripple through the network, which is why visibility and coordination matter as much as any single function’s efficiency.

New objectives

Cost and service were the classic goals. Resilience (surviving disruptions) and sustainability (emissions, social impact, circularity) have joined them, and many supply chain decisions now trade off all four.

Interview kit

Practise it out loud

Answer each question yourself before opening the model answer.

Say it in 30 seconds

A supply chain is all the stages involved in fulfilling a customer request: suppliers, manufacturers, distributors, retailers and the customer, connected by flows of product, information and funds. The goal is to maximize the total value created, not to optimize each stage separately. A key design choice is the push–pull boundary: steps before it run on forecasts, steps after it respond to actual orders, and inventory sits at the boundary.

What is the push–pull boundary, and where is it for a shampoo versus a custom laptop?

It’s the point where the supply chain switches from forecast-driven to order-driven work. For shampoo it’s at the store shelf: everything up to there is made and moved on forecasts. For a made-to-order laptop it’s at assembly: components are pushed to the factory, but final assembly happens only after the order.

Why optimize the whole supply chain rather than each stage?

Because stages trade off against each other. A factory minimizing its own cost might run huge batches, which raises warehouse and obsolescence costs downstream. Only a total view finds the lowest overall cost at the service customers need.

Connected stops

Where this idea feeds in, or gets its inputs from.

Sources and further reading

  1. Chopra, S. & Meindl, P. Supply Chain Management: Strategy, Planning, and Operation. Pearson. Chapter 1: understanding the supply chain.
  2. Christopher, M. Logistics & Supply Chain Management. Pearson.
  3. Oliver, R. K., & Webber, M. D. (1982). Supply-chain management: Logistics catches up with strategy. Outlook, Booz Allen Hamilton.

Reading settings

Saved on this device. Changes apply as you choose them.

Theme
Text size
Typeface for reading
Line spacing
Line length
Start each topic at

Deeper levels stay one click away whichever you choose.

Preview

Safety stock covers the surprises while you wait for a delivery. It grows with the square root of lead time, not with lead time itself.

Lines

↑ ↓ move ↵ open Topics marked “Soon” open their line